Parrish Gap Substation
PacifiCorp’s current system is experiencing overload conditions in multiple locations. A a new 230/69kV substation is needed to meet demand in western Oregon – and the project needs to be built as soon as possible. The below-grade design package needs to be completed in only two months in order complete construction of the first phase before winter frost. DEA is working closely with PacifiCorp to prepare the siting and permitting support to get the project approved by the county. We are also proceeding with the design work required for the project.